Installation Position Requirements; Installation Space Requirements - Pytes HV48100 User Manual

Lifepo4 energy storage battery
Table of Contents

Advertisement

Cleaning
The battery system is equipped with high voltage connectors. Cleaning conditions will affect
isolation characteristic of the system. Before system installation and operation, dust and iron
scurf must be cleaned. An anti-dust environment is recommended. Turn off the system to
clean if it's over operation conditions.
Operation Temperature
HV48100 system operation temperature: -20℃~60℃;
Optimum range: 18℃~28℃.
WARNING
Out of operation temperature will lead to battery system over / low temperature alarm or
protection, which reduces battery cycle life.
Grounding system
Make sure the system is well grounded before installation.
The resistance of the grounding system must ≤100mΩ
Installation Angle Requirement
The battery can be floor-mounted only.
Do not install the battery at forward tilted, back tilted, side tilted, horizontal, or upside down
positions.

4.3.2 Installation Position Requirements

Install the battery on a solid brick-concrete floor. If other types of floors are used, they must
be made of fire-retardant materials and meet the load-bearing requirements of the equipment.

4.3.3 Installation Space Requirements

During installation, ensure that there are no other devices (except related Pytes devices and
awnings) or flammable or explosive materials around the batteries. Reserve adequate space
for heat dissipation and safety isolation.
Keep enough space for the batteries, recommended as below:
22

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the HV48100 and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Hv48100 bmu-5Hv48100 bmu-6Hv48100 bmu-7Hv48100 bmu-8Hv48100 bmu-9Hv48100 bmu-10 ... Show all

Table of Contents