General test notes

Note
To secure the power unit against restarting, +F03-FC22 must be enabled and secured against
restarting. +F03-FC22 enables the motor switch of the main switch. If +F03-FC22 is not
accessible, +F01-QA2 can be enabled as an alternative and protected from restarting.
• Follow the order for testing described below: Inspecting – Measuring – Testing
• Start the measurements with testing the continuity of the protective equipotential
bonding
• The insulation test must be conducted without a connected supply cable. Remove any
installed PEN bridge
• Remove the back-up fuses and connector modules of the surge protection devices prior to
the insulation measurement:
– +F01-FC1
Version with basic surge protection device
Version with extended surge protection device
SICHARGE D - Testing according to DIN VDE 0100-600
Commissioning Manual, 01/2024, A5E52910486-AC