Your Sany Equipment; Breaking In A New Equipment - SANY SCM2000C-8S Safety, Operation & Maintenance Manual/Parts List

Milling machine
Table of Contents

Advertisement

Introduction
maintenance or repair operations on the
equipment.
6. Troubleshooting
This section outlines common malfunctions
and fault diagnostic procedures for the operat-
ing system. Basic mechanical, hydraulic and
electrical system troubleshooting is included.
7. Technical Specifications
This section provides the basic performance
parameters of this equipment.
Some information may change as design
modification.

1.3 Your Sany Equipment

1.3.1 Breaking in a New Equipment

Your equipment has been well adjusted and
tested before delivery, but the initial operation
on the machine in severe conditions will seri-
ously affect the performance or reduce the
service life of the machine. Thus Sany recom-
mends you to perform 100-hour test run be-
fore putting the equipment into production
use.
During the test run:
Preheat the equipment before performing
any operations.
Avoid operating or running the equipment at
a
high
speed
conditions.
Avoid sudden starting, rapid movement or
abrupt stop of the equipment.
Cool down the equipment system at the
end of every working day.
1-6
in
overload
working
Safety, Operation and Maintenance Manual-April 2020
SCM2000C-8S Milling Machine

Advertisement

Table of Contents
loading

Table of Contents