(1) Stop the pump, and set the inside of the pump to the atmospheric pressure.
(2) Shut the electricity supply and remove the cable connection.
(3) Remove the Cooling water piping.
(4) Discharge the lubrication oil from the cover of Gear side and the Pulley side.
(5) Remove the Suction/exhaust piping and put Blind flanges to the Pump inlet and outlet to seal
them up.
●This pump cannot be used with harmful gas or combustible gas.
However, if it is accidentally used to exhaust harmful gas, the pump
body and, of course, the pump oil also become harmful. Take due
care.
●Before removing the pump used to exhaust particular gas,
sufficiently replace it with nitrogen gas.
In addition, any persons other than qualified particular gas handlers
are not allowed to remove the pump.
●Attach a label indicating the name of the gas in use to an easy to see
position on the pump.
●You have a risk of giving damage to your back as the load larger than
safety standard shall be required to transfer the product.
PMB-040C:970kg(Without Motor)
PMB-060C:1100kg(Without Motor)
Be sure to use the loading machinery (such as mobile crane) to lift up
the Pump or load it on the pallet and fix it with Jack and run the Pallet
truck for its transfer.
●Never try to enter beneath the Pump unit when lifted it up. Use the
accessory eyebolt to load/unload the unit.
●Do not put the folk of the Fork lift or the like in the Pump bottom
(exhaust outlet) to lift it.
●Note to purge the oil to transfer the pump. If forced to transfer
remaining the oil, be sure to keep the pump horizontal. Do not tilt the
pump 10 degree or more while you charge the oil. The oil might run
into the casing.