Smartrise HYDRO:EVOLVED Startup Manual

Soft starter
Hide thumbs Also See for HYDRO:EVOLVED:

Advertisement

Quick Links

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the HYDRO:EVOLVED and is the answer not in the manual?

Questions and answers

Summary of Contents for Smartrise HYDRO:EVOLVED

  • Page 3 Soft Starter Startup Manual Siemens Document History Date Version Summary of Changes January 30,2021 Initial Submittal January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page i...
  • Page 4 Soft Starter Startup Manual Siemens Page intentionally left blank Page ii © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 5: Table Of Contents

    Wrong Direction ........................9 Car Not Moving or Too Slow ....................9 No Control ..........................9 Appendix 1 Siemens LCD Troubleshooting Chart ........... 10 Appendix 2 Terminal Locations ................15 January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page iii...
  • Page 6 Figure 9: SETUP Menu – Miscellaneous......................... 7 Figure 10: MISCELLANEOUS Menu – Bypass Term Limits ....................8 Figure 11: Bypass Term Limits Menu ..........................8 Figure 12: Terminal Locations ............................15 Page iv © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 7 Soft Starter Startup Manual Siemens List of Tables Table 1: 6/12 Lead Delta Motor Wiring ......................... 4 Table 2: 3/9 Lead Line Motor Wiring ..........................4 Table 3: Troubleshooting Solutions..........................10 January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page v...
  • Page 8 Soft Starter Startup Manual Siemens Page intentionally left blank Page vi © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 9: Siemens Soft Starter

    Figure 1: Siemens Soft Starter Equipment/Settings Verification Set and verify the equipment matches the job specific parameters for proper operation. See Hydro:Evolved sheet 3 Table for more information. Figure 2: Example of Parameter Table January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved...
  • Page 10: Grounding Requirements

    A checklist must be completed during the soft starter wiring process. See Appendix 2 for terminal location. Power Perform the following to connect power. See the Hydro:Evolved sheet 7 for job specific information. • Connect main line power L1/L2/L3 to soft starter.
  • Page 11: Valve Board

    5. Connect UPH, UPL, DNH, and DNL from the solenoids to the Valve board. Motor/Soft Starter Perform the following to connect the soft starter to the motor. See the See the Hydro:Evolved sheet 8 for job specific information for job specific information.
  • Page 12: Figure 5: 3-Lead Line Wiring Configuration

    Table 2: 3/9 Lead Line Motor Wiring Terminals Jump 3-Lead Motor (208-575 VAC) 9-Lead Motor Low (220-240 VAC) 1,6,7 2,4,8 3,5,9 High (460-480 VAC) 4 and 7 5 and 8 6 and 9 Page 4 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 13: Construction

    Soft Starter Startup Manual Siemens Construction All safety inputs are functional during Construction mode on the Hydro:Evolved controller. When these safety devices are installed, they are connected even if still on Construction mode. See page 5 for safety input connections. The following includes instructions for when none of these devices have been installed prior to beginning on Construction mode.
  • Page 14: Powering Up

    Perform the following to power up the soft starter. Complete the checklist during the verification process. 1. Apply external power by closing the main disconnect. 2. Close the two-pole breaker and all pushbutton breakers. Page 6 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 15: Final Setup

    4. From the MAIN MENU, scroll and select Setup. Figure 8: MAIN MENU – Setup 5. From the SETUP menu, scroll and select Miscellaneous. Figure 9: SETUP Menu – Miscellaneous January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page 7...
  • Page 16: Operation

    If the inspection speed is less than contract speed the car should move with leveling speed. See Car Not Moving or Too Slow for troubleshooting at speed faults. Page 8 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 17: Under Control

    Troubleshooting The following sections list troubleshooting procedures. Soft Starter Fault If the Smartrise controller indicates a soft starter fault and the soft starter has the fault LED flashing, see Appendix 1 Siemens LCD Troubleshooting Chart. Wrong Direction If the motor is running in the wrong direction, swap any two motor leads.
  • Page 18: Appendix 1 Siemens Lcd Troubleshooting Chart

    Fault ROM The starter has Replace the starter. Memory detected a problem with the ROM memory. Fault The starter has Replace the starter. Watchdog detected an internal fault. Page 10 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 19 Consult technical support for further assistance. January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page 11...
  • Page 20 If the meter reading matches the starter’s reading, correct the voltage problem. If the meter reading does not agree with the starters voltage reading, contact technical support. Page 12 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 21 To view the exact line incoming three voltages when the fault occurred, view phase power during the diagnostic screen via a laptop a run condition. computer or PDA. January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page 13...
  • Page 22 “All 3 Phases” and one winding’s current is significantly higher than the other windings, nuisance overload trips may occur during long up runs near or at the rated up load. Page 14 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...
  • Page 23: Appendix 2 Terminal Locations

    Soft Starter Startup Manual Siemens Appendix 2 Terminal Locations Figure 12: Terminal Locations January 30,2021 ©2021 Smartrise Engineering, Inc. All Rights Reserved Page 15...
  • Page 24 Soft Starter Startup Manual Siemens Page intentionally left blank Page 16 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30,2021...

This manual is also suitable for:

Hydro evolved

Table of Contents