Prepare the installation site.
Provide drainage, water supply and electrical power to within 6 feet (2m) of ice
machine in accordance with local and national codes. Outdoor installation is
not recommended and will void warranty.
2.1
2.1
Installation site requirements
Electrical
• 120/60/1-5 amps
Potable water supply
• 10-70 psi (69-483kpa)
• 45-90 F (7-32 C)
• Follett recommends the use of an in-line water filtration system (item# 00130286)
• This equipment is to be installed with adequate backflow protection to comply with applicable
federal, state, and local codes
Drain
(3/4" MPT)
• The drain line from the ice machine must have at least 1/4" per foot pitch (6,4 mm/0,3 m)
Refrigeration lines
• 5/8" ∅ (15,8 mm) diameter suction line (insulated)
• 3/8" ∅ (9,5 mm) liquid line
ICE MANAGER
1/4" per foot
(6,4 mm per 0,3 m)
(3/8" push-in internal connection, 3/8" OD tubing required)
remote condensing
1'

Site preparation

NEMA
5-15
3/8" ∅ (9,5mm)
5/8" ∅ (15,8 mm)
2
5

Advertisement