3.6 Nailing Flange Assembly and Installation

Note: If installing the Finishing Trim Kit (recommended)
please complete that prior to installing the nailing flanges.
CAUTION: Never permanently remove these assemblies
from the fireplace. They must be secured regardless of
finish material used.
1.
Remove (2) nailing flanges from the right and left side
of the fireplace.
2.
Align nailing flange with holes on outside corners of
fireplace, with the stand-off flanges on the nailing
flanges facing away from the fireplace
Figure 3.2 - Nailing Flange Installation
Hussong Mfg. Co, Inc.
NDK-36-DV - PFS Report No. 23-152
3. Secure the nailing flanges to the fireplace with screws
(provided) through the slots in nailing flanges.
4. Bend perforation on nailing flange until parallel with fire-
place face. Do not bend toward fireplace face.
5. Position framing stud against the small stand-off (located
on backside of nailing flange). Secure with nails or screws.
When installed, the nailing flanges provide the minimum
7/16" (11mm) clearance from the sides of the fireplace to
framing.