Test Setup and Procedure

2 Test Setup and Procedure

2.1 EVM Connections

Referencing the EVM connections described in
to evaluate the TLVM13610. Working at an ESD-protected workstation, make sure that any wrist straps,
bootstraps, or mats are connected and referencing the user to earth ground before power is applied to the
EVM.
Power Supply
Ammeter 1
-
+
A
V
COM
Voltmeter 1
SPACER
LABEL
VIN+
VIN–
VOUT+
VOUT–
LABEL
VIN S+
Positive input sense terminal. Connect the multimeter positive lead for measuring efficiency.
VIN S–
Negative input sense terminal. Connect a multimeter negative lead for measuring efficiency.
VOUT S+
Positive output sense terminal. Connect a multimeter positive lead for measuring efficiency and line and load regulation.
Negative output sense terminal. Connect the multimeter negative lead for measuring efficiency and line and load
VOUT S–
regulation.
GND
Ground reference point
SW
Switch node monitor output
4
TLVM13610EVM Buck Regulator Evaluation Module
Table
Oscilloscope
COM

Figure 2-1. EVM Test Setup

Caution Hot surface.
Contact may cause burns.
Do not touch.

Table 2-1. EVM Power Connections

Positive input power connection
Negative input power connection
Positive output power connection
Negative output power connection

Table 2-2. EVM Signal Connections

Copyright © 2023 Texas Instruments Incorporated
2-1, use the recommended test setup in
CAUTION
DESCRIPTION
DESCRIPTION
www.ti.com
Figure 2-1
Ammeter 2
Electronic Load
A
+
COM
V
COM
Voltmeter 2
SLVUCN1 – JANUARY 2023
Submit Document Feedback
-

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TLVM13610EVM and is the answer not in the manual?

Table of Contents