Ceiling (Box #1):
 Install 4 large Styrofoam packing squares on top of the Right & Left Wall panels. One block
should be placed in the front portion and one toward the rear portion of each wall. These will
be used to set the ceiling on.
 The ceiling can now be set in place on top of the Styrofoam blocks.
Once the Ceiling panel is lined up directly above the Wall panels; insert the wires harnesses
from the wall panels into the holes in the Ceiling panel.
Note: Position the cam locks on the top of the Left & Right Wall panels as shown above.