After concrete has cured completely and anchors have cured completely into place:
1. Position washer over the mounting anchors.
2. Raise the washer 12.7mm (1/2inches) off the mounting surface and place spacers under
the corners of the washer base.
3. Level the washer, leaving washer at least 12.7mm (1/2inches) off the mounting surface.
Do not permanently support the washer with spacers under the corners. Machine must
be grouted, and spacers must be removed.
4. Mix non-shrinking machinery grout according to the grout instructions. The grout should
not be too runny or too firm. Completely fill the 12.7mm (1/2inches) space between
the washer base and the mounting surface. Force grout under all base angles and plates
until completely filled. Fill around all anchor bolts.
5. Finger tighten all nuts to anchor bolts.
6. When the grout has started to stiffen (but before it is cured), remove the spacers from
the corners and allow the washer to settle into the wet grout. Fill in any voids as
necessary with additional grout.
7. Allow grout to completely cure, then tighten all nuts to securely fasten the washer to the
grouted mounting surface.
8. Retighten nuts after 5 days of operation and check quarterly.
If using a steel mounting base, first grout the steel mounting base to the concrete floor
using the above steps, then repeat the steps for mounting and grouting the washer to
the steel mounting base.
8514-300-001 REV PR