6.6.1 Connecting the waste water line to a permanent connection
INFORMATION
Prerequisite The waste water line complies with the specifications (see "Unit and
Technical qualifications for waste water installation tasks
Waste water installation tasks on waste water lines and the unit may
be carried out only by a waste water specialist provided by the
specialist company contracted.
c
d
b
e
a
f
Image: Waste water line with vacuum breaker to a permanent connection
a Waste water mains
b Waste water line
c Vacuum breaker
Install a vacuum breaker in the waste water line.
connection data")
1. Install waste water line up to connection to the waste water
system.
2. Secure waste water line with pipe clamps.
3. Fill the siphon of the unit with drinking water.
4. Fill out the Start-up operation report.
Installation instructions
Connecting the unit
d Pipe clamp
e Waste water connection
f Waste water mains siphon
35