User manual
SERIES 1500 LIQUID TURBINE METER
P/N 3-9008-515
7
Testing
7.1
Test the turbine meter
7.1.1
Commission the turbine meter
After installation, commission the turbine meter to ensure that the equipment is working
properly.
Procedure
1. Inspect all electrical connections to ensure compliance with electrical codes and
2. Inspect all flange bolts used to secure the turbine meter in-line to ensure that
3. Evaluate the system setup to ensure that all components are in the correct
4. Ensure that the supply voltage to the preamplifier is within the 10-30 VDC range.
70
www.Daniel.com
User manual
safety regulations.
correct mounting procedures are followed and that flange connections are leak-
free.
sequence for accurate product measurement: isolation valve, strainer, flow
straightener, turbine meter, downstream section, control valve, etc.
Testing
March 2019
77