7.3 Assembling, Installation and Levelling

Remove the four transport securing devices above the supports of the weighing
platform
Install weighing plate and wind shield if necessary.
Ensure that the balance is installed in a level position.
Level balance with foot screws until the air bubble of the water balance is in the
prescribed circle.
Check levelling regularly

7.4 Mains connection

Select a country-specific power plug and insert it in the mains adapter.
Check, whether the voltage acceptance on the scales is set correctly.
Do not connect the scales to the power mains unless the information on
the scales (sticker) matches the local mains voltage.
Only use KERN original mains adapters. Using other makes requires
consent by KERN.
Important:
Before starting your weighing balance, check the mains cable for
damage.
Ensure that the power unit does not come into contact with liquids.
Ensure access to mains plug at all times.

7.5 Battery operation (optional)

When the batteries are exhausted, in the display will appear <Lo Bat>.
Rotate the balance carefully in a way that the bottom of the balance is freely
accessible.
Open the battery compartment and exchange the batteries.
Ensure correct polarisation.
Close again the lid.
• To save the battery, in menu (see chap. 13.3.1.) the automatic switch-off
function < Autoff > can be activated.
• If the balance is not used for a longer time, take out the battery and store
it separately. Leaking battery liquid could damage the balance.
TFKB_B-BA-e-2210