When 24Vdc power is first applied to the Energy Pack, the power-up process goes
through the following steps:
The IN LED turns on green.
1.
The Energy Pack performs a self-diagnostic test. If this test passes, output
2.
power to the Controller is turned on and the OUT LED turns on green.
Charging of the CapPack begins and the STAT LED blinks green.
3.
When charging of the CapPack is complete, the STAT LED turns on solid green
and the Energy Pack signals to the controller that it can start run-time
operation. The Controller will not start running its application until the Energy
Pack signals that it is fully charged.