PHASE 10: TESTING
To commission the unit it is necessary to (tick "√" the operations completed):
check for accurate fluid inlet and outlet pipe connections to the coils (if applicable)
Check that there is a suitable siphon for all the water being drained.
check unit integrity;
check that the installation of the sections is correct (only for size 5-6-7)
check that the electrical connections have been made correctly
Remove extraneous materials (e.g., assembly sheets, tools, clips, etc.) and dirt (footprints, dust, etc.) from inside the sections.
PERSONAL PROTECTIVE EQUIPMENT
Personal protective equipment should be used when operating the unit, suitable for use in accordance
with company criteria and rules.
During unit maintenance, other preventive measures are suggested in addition to the above: safety shoes,
gloves, suitable clothing, always compatible with the use and according to company guidelines.
TRAINING
It is the responsibility of the unit buyer/user to provide adequate instruction and training to unit operators.
OPTIONAL
In agreed cases, additional training may be provided through the one-on-one instruction of operators by
the Manufacturer's technical staff.