CRITERIA FOR INSTALLING THE PERIMETER CABLE

4.4.1. PERIMETER CABLE PLACEMENT

Procedure:
1. If there is a pavement or path (A) at the same level as the lawn, arrange the perimeter cable (B) at
X1 = 5 cm from the edge of the pavement.
2. In the vicinity of a level fl ower bed, a metal manhole, a shower surface or electrical cables, arrange
the perimeter cable (C) at least X2 = 30 cm away.
B
3. If there is an obstacle, for example a ditch (D), a wall or a low wall (E), arrange the perimeter cable
(F) at least X3 = 35 cm from the obstacle.
F
D
EN
A
F
E
4. INSTALLATION
C