4.11 Verifying the Installation

You need to carefully check items 08 and 09 listed in the table. If the check results
of these two items do not meet the acceptance criteria, the UPS may be damaged.
Table 4-12 Checklist
No.
01
02
03
04
Issue 03 (2022-11-29)
NO TICE
Check Item
Cabinet installation
Neat arrangement
Layout of the busway and
cables
Labels on the busway and
cables
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
Acceptance Criteria
The cabinets are securely installed and
do not tilt due to vibration.
The UPS and its adjacent cabinets are
neatly arranged and secured with
connecting kits.
The busway and cables are routed
properly as required by the customer.
Both ends of a busway and cable are
labeled. Labels are concise and easy to
understand.
142