6. Commissioning, operation
6. Commissioning, operation
6.1
Connecting the CPU6000 series
WARNING!
Only assemble and connect the instruments when they are switched
■
off!
Only use the AC adapter from WIKA supplied with the instrument!
■
Never connect any electrical cables longer than 3 metres!
■
Before commissioning, connect all instruments that are to be measured. An errone-
ous connection of individual components is prevented due to the different male/female
connector combinations.
When connecting an electronic pressure transmitter, pay attention to the
correct polarity.
The correct pin assignments are shown in the technical drawings (see chapter
3 "Specifications").
If a wall mount is integrated into the instrument, the CPU6000 can be mounted on a wall
or under a table, for example. The position is irrelevant for both the measurements and
the communication with PC/laptop or iPad
WIKA operating instructions CalibratorUnit, model CPU6000
®
.
EN
25