Tests and Adjustments
ANSI/NCSL Z540.3–2006 and ISO/IEC 17025 Verification
ANSI/NCSL Z540.3–2006 and ISO/IEC 17025 Verification
To meet the criteria for ANSI/NCSL Z540.3–2006 and ISO/IEC 17025, perform
the preliminary checks and all performance tests without stopping to repair or
adjust
tests, even if you are aware that the analyzer did not pass. If there is a failure,
complete the verification before you troubleshoot, repair, and adjust. After the
failure has been corrected, repeat the entire set of performance tests and
generate a new set of data.
Figure 3-1
ANSI/NCSL Z540.3–2006 and ISO/IEC 17025 Verification Flowchart
3-10
1
. Refer to
Figure 3-1
1. Stop only in case of a catastrophic failure or cable connector damage
for test flow. Print data at the completion of all the
Keysight N5224B/25B Service Guide