Heat Radiation Countermeasures - Mitsubishi Electric E70 Series Connection Manual

Hide thumbs Also See for E70 Series:
Table of Contents

Advertisement

MITSUBISHI CNC
3 Installation

3.1 Heat Radiation Countermeasures

Please refer to the following method for heat radiation countermeasures.
Example of heat radiation countermeasures
<Hypothetical conditions>
(1) Average internal temperature of operation panel: T ≤ 55°C
(2) Peripheral temperature of operation panel : Ta ≤ 0°C to 45°C
(3) Internal temperature rise value : ΔT = T - Ta (max) = 10°C
Procedures for heat design and verification
Calculate total heat radiation of each
mounted unit (W)
W
W1
Collection of internal temperature rise
distribution data
ΔT
10°C
<Supplement>
(1) Refer to "General Specification" for the heat generated by each unit.
(2) Enclosed cabinet (thin steel plate) cooling capacity calculation equation
W1 = U × A × ΔT
U: 6 W/m
A: Effective heat radiation area (m
ΔT: Internal temperature rise value (10°C)
(Caution) 8 W/m
(3) Points of caution for heat radiation countermeasures when designing mounting state
- Consider convection in operation panel (eliminate heat spots)
- Collect hot air at suction port of heat exchanger in operation panel.
(4) Criterion for internal temperature rise distribution data
ΔT (average value) ≤ 10°C
ΔTmax (maximum value) ≤ 15°C
R (inconsistency ΔTmax - ΔTmin) ≤ 6°C
(Evaluate existence of heat spots)
62
Calculate cooling capacity of
operation panel (W1)
Comparison of W and W1
W>W1
Selection of heat exchanger
Mounting design
Evaluation
ΔT>10°C
Improvements
Completion
2
°C
2
) (Area where heat can be radiated from operation panel)
2
°C can be applied only when the operation panel is so small that the internal
temperature stays uniform.