7. Steps for Connecting

This section describes the procedures for setting up an Ethernet connection on the controller
(PCL).
The explanations of procedures for setting up the PLC and smart camera given in this
document are based on the use of the factory default settings. If re-initializing the devices is
required, refer to Section 8. Initialization Method.

7.1. Operation Flow

Use the following procedures to set up an Ethernet connection on the controller (PLC).
7.2. Smart Camera Setup
7.2.1. Install the (AutoVision) software
7.2.2. Set Parameters
7.3. Controller Setup
7.3.1 Start Sysmac Studio and load the
project file
7.3.2 Verify parameters and execute
builds
7.3.3 Connect online and transfer
project data
7.4 Check the Connection Status
7.4.1. Run the project file and confirm
the receive data
Precautions for Correct Use
Please prepare the latest file of "Sysmac Studio project file" from Omron Corp. beforehand.
(Contact Omron for information on how to obtain these files.)
Set up the Smart camera.
Install the (AutoVision) software application used for
setting up the Smart camera.
Set the parameters for the Smart camera.
Set up the Controller.
Start the "Sysmac Studio" (Automation Software)
and load the Project File in to Sysmac Studio.
Check the configuration parameters and execute
program check and build of the project data.
Connect online in Sysmac Studio and transfer the
project data to Controller.
Execute the transferred project file and check that
Ethernet communication is performed correctly.
Run the project file and check that the correct data is
written to the controller variable.