Test Setup

5.1

Test Equipment

Voltage Source: One 5-volt power supply with at least 0.5-A sourcing capability. (Optional) One DC
power supply with adjustable voltage from 0 V to 3.3 V.
Multimeters: One voltmeter
Output Load: Optional
Oscilloscope: Optional
Fan: None
Recommended Wire Gauge:AWG 24, or thicker
To Test Configuration, Monitoring and Control Functionality
Recommended PC platform: Windows 7, 64-bit with 8-GB RAM
USB Interface Adapter EVM (USB-to-GPIO): HPA172
The latest version Fusion Digital Power Designer software can be downloaded at the following link
to the Texas Instruments website:
http://focus.ti.com/docs/toolsw/folders/print/fusion_digital_power_designer.html
5.2

Recommended Test Setup

Figure 2
illustrates the recommended test setup.
SLVUAF3A – March 2015 – Revised March 2015
Submit Documentation Feedback
Figure 2. UCD90240EVM-704 Recommended Test Setup
Copyright © 2015, Texas Instruments Incorporated
UCD90240EVM-704 24-Rail Sequencer Development Board
Test Setup
5

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the UCD90240EVM-704 and is the answer not in the manual?

Table of Contents