Section 6c Start Up Procedures
6c.1
Controller Inspection
WARNING:
Read Section 2 and 3 on Personal and Equipment Safety completely before starting
this procedure.
Read Section 4 on Installation Considerations - completely before starting this
procedure.
Read this section completely before beginning the start up procedure.
Have someone stand by the main line disconnect during the following phases of the
start up procedure for added safety:
- First time power on of the controller.
- First time an attempt is made to move the car.
Insure all safety circuits are functional.
Insure all hoistway door interlocks are electrically functional.
Insure car gate circuitry is electrically functional.
Prior to Applying Power:
Verify all circuits are wired to the controller properly.
Check the following items:
MPU switch down
INSP switch down
DDS switch down
NON/RESET switch down (For troubleshooting purposes)
MG switch down (Amicon)
Verify, with an ohmmeter, that the governor overspeed switch and any other devices
that are wired in at this time will open the safety circuit.
Physically verify that all hoistway doors are closed and locked.
Verify that the tach or encoder leads are wired to the motor drive system in the
appropriate place.
Verify that the main line power supply voltage is the same as the controller order as
seen on the prints shipped with the controller.
Revision: AA 2.2
Microflite Ultra 2000 - Amicon Regulator
Amicon Regulator
-
Note: NON/RESET switch up (When in automatic)
Printed 03 - 15 - 03
6c - 1