Maintenance plan

The results of all the regular inspections are to be documented and kept available at the company.
The written result of the last inspection must be kept available at the site of operation, e.g. by an
inspection sticker on the Roll Down showing the date of the inspection, the basis of the inspection
and the name of the inspector.
Before every use and weekly
Every time when rigging the Roll Down, before running the Roll Down – and at least every week
when the Roll Down is in use:
Check that the Roll Down is safely and correctly installed/mounted.
Inspect the entire length of the tube for bends, damage, wear, and abuse.
Inspect the fabric attachment for damage, wear, or abuse.
Check that the fabric winds neatly around the tube
Check that the fabric weighs maximum 35 kg (77 lb).
Check all safety devices (limit switches, and emergency stop)
Check that the Roll Down's LEDs are visible from the operating station.
Make sure that the operator has visual confirmation of all possible movements of the Roll
Down at all time.
Monthly
At regular intervals – but at least every month when the Roll Down is in use:
Check the mounting clamps for damages and proper fastening.
Change damaged parts according to this manual.
Yearly
The Roll Down has to be inspected by a specialist every 12 months.
Every 48 months
The Roll Down should be inspected by an authorised expert every 48 months.
Checklist
Use the checklist accordingly; before each use, each month etc.
Check
Installed / mounted correct
Load and LEDs visible for the operator
Entire tube length OK
Emergency stop
Fabric is wound neatly around the tube
Fabric attachment
powerCON TRUE1
249.805.013
Type
Inspection
Inspection
Inspection
Functional test
Inspection
Inspection