Commissioning

3
Commissioning
3.1

Oil supply

3.1.1
Introduction
In all operating states, a functioning and carefully executed oil supply is an important
prerequisite for trouble-free operation of the turbocharger.
The lubrication of the turbocharger is usually carried out with oil from the engine oil circulation.
Follow the enginebuilder's specifications on the selection of the lubricating oil and the oil
change intervals.
3.1.2
Pre-lubrication
Pre-lubrication must be carried out as follows:
Switch on the oil pump.
Build up oil pressure (see Table 6).
Do not exceed a pre-lubrication time of 2 minutes.
Start the engine.
Let the oil pump run until the pump driven by the engine generates sufficient pressure.
3.1.3
Oil filtering
Lubricating oil filtering with a filter mesh width of ≤ 0.034 mm is sufficient for this turbocharger.
3.1.4
Oil pressure
Comply precisely with the oil pressure before the turbocharger for trouble-free operation.
The admissible values are specified in chapter Monitoring operation [➙ 29].