Commissioning; Required Qualification; Commissioning Procedure; Commissioning Checklist - ABB ACS6080 User Manual

Hide thumbs Also See for ACS6080:
Table of Contents

Advertisement

7. Commissioning

7.1. Required qualification

Commissioning, parameter adjustments and functional tests must be carried out only
by qualified commissioning personnel that have been certified by ABB.

7.2. Commissioning procedure

Information on the commissioning procedure and the start conditions for
commissioning can be obtained from ABB.

7.3. Commissioning checklist

In order to ensure uncomplicated and speedy commissioning, it is important that drive
and associated equipment are ready for commissioning. Reviewing and completing the
items in the commissioning checklist before the commissioning personnel arrive on
site will help to achieve this.

7.4. Customer assistance

During the commissioning period, the customer is requested to provide qualified
personnel for assistance, who are:
Experienced with medium and low voltage equipment and with the local
safety regulations,
Familiar with the driven process
Authorized to operate associated medium and low voltage equipment (eg, input
circuit breaker, other low and medium voltage switchgear)
Authorized to operate the driven process for functional tests

7.5. Customer acceptance

When commissioning has been completed, the commissioning report is signed by the
responsible commissioning personnel and by the customer as a sign of acceptance. A
copy of the report and a copy of the actual parameter settings are handed out to
the customer.
PRODUCT
ACS6080
DOCUMENT KIND
User manual
DOCUMENT ID.
3BHS842007 E01
COMMISSIONING
REV.
LANG.
PAGE
I
en
140/211

Advertisement

Table of Contents
loading

Table of Contents