Commissioning Work - Beko CLEARPOINT 3eco S040 Original Installation And Operating Manual

Coalescing filter
Table of Contents

Advertisement

CLEARPOINT
®
3eco
coalescing filter

8.2 Commissioning work

The following requirements must be fulfilled to carry out commissioning work and preparatory work must be completed.
Tool
none
1.
Completed installation with leak test
Automatic drainage
34 | 60
Preconditions
Material
none
Preparatory work
Picture
Mechanically open
Installation and operation instructions
Protective equipment
none
Description
1. Turn knurled screw on the float drain from
"Mechanically open" counterclockwise
(left-hand thread) to "Automatic
drainage".

Advertisement

Table of Contents
loading

Table of Contents