8. Commissioning
8.1 Commissioning tasks
For commissioning to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must have
been completed.
Tools
•
none
1.
Assembly finished including subsequent leakage test
•
none
Preparatory tasks
Illustration
1
3
2
CLEARPOINT
Prerequisites
Material
Description
1. Open the shut-off valve [1] on the inlet
side slowly
2. Open the shut-off valve [2] on the outlet
side slowly
3. Close the shut-off valve [3] of the bypass
pipe
V activated carbon filter with cartridge
®
Protective equipment
•
None