9. Remove the eyebolts and fasten the bollard to the pit using the ten
M12x30 screws and the eight M16x30 screws. Apply the fastening
torques given in  9.
45 Nm
90 Nm
10. Fasten the cover to the frame using the eight M6x20 screws.
To reposition or lift the cover, prise one of the two slots upwards using
a screwdriver.
J275 HA 2K20

5.2 MANUAL OPERATION

!
Before carrying out the release procedure, disconnect the power supply
to the automation system.

RELEASE PROCEDURE

1.  11 Remove the plugs 1 and unscrew the screws 2.
24
10
2. Unscrew the plug 3.
 9
5
3. 12 Insert the key 1 and turn it anticlockwise until it stops 2.
 1 0
11
1
T30
3
2
1
2