Verifying Line Connection
Touch the red multimeter lead to the line/hot connection and touch the black lead to the
ground lug. The meter should display a voltage verifying the presence of 230 VAC.
Verifying Neutral Connection
Touch the red multimeter lead to the neutral connection and touch the black lead to the ground
lug. The voltage value should not exceed 5 VAC.
Verifying Operating Voltage
Touch the red multimeter lead to the line/hot connection and touch the black lead to the
neutral. The meter should display a voltage value of 230 VAC ± 10%.
NOTE
All panel locks need to be in the lock position in order for rack to be properly grounded.
NOTE
After confirming line and neutral connections and the operating voltage is within the
specified range, power up the Vertex Edge® and check the operating voltage again to assure
the voltage under load is within the specified range for safe operation.
Vertex Edge Transformer Installation
The directions and diagrams enclosed herein are intended to illustrate the proper installation
and wiring of transformers designed to step-down or step-up site voltage to proper levels for
Vertex Edge System
NOTE
Shown is the locked position, which
provides ground to the panel.