COMPONENT MAINTENANCE MANUAL
F.
Bowl Flushing Test
(1) Fill the toilet tank to the specified precharge level (see Leading Particulars).
(2) Upon flushing the toilet it should be observed that the bowl is completely wetted and
water action is vigorous without excessive splashing.
(3) Repeat flushing operation four times to confirm adequate bowl coverage and water
action.
(4) Drain toilet.
G.
Liquid Level Sensor Test
(1) Connect the liquid level sensor to the appropriate test harness.
(2) Fill the toilet tank to the precharge level.
(3) Ensure that the precharge indicator light is on.
(4) Continue filling the toilet tank to the full level as indicated in the drawing.
(5) Ensure that the full indicator light is on, and the solenoid valve is shut off.
H.
Leak Test
(1) Cap the tank vent. Fill the toilet throughout the bowl aperture until the water level is
approximately one inch below the bowl flushing ring.
(2) Remove any air trapped within the tank.
(3) Allow the toilet to remain in this condition for one hour after which there shall be no
evidence of leakage from any of the toilet components, including the toilet tank, tank
top, gaskets and fitting.
I.
Disconnect water supply.
J.
Disconnect power supply.
K.
Drain all water from tank and remove all water from components.
Monogram Sanitation
PN 15900-012 Series
38-31-07