Procedure
Step 1 Installing AC input power cables of the parallel box
----End

6.9 Verifying the Installation

Table 6-6 Check items and acceptance criteria
No.
1
2
3
4
Issue 01 (2021-09-30)
Check Item
Product installation
Cables routing
Cable bonding
Grounding
Copyright © Huawei Digital Power Technologies Co., Ltd.
6 Electrical Connection
Expected Result
The installation is correct and reliable.
Cables are routed properly as required
by the customer.
Cable ties are evenly distributed and no
burr exists.
Ground cables are connected correctly
and securely.