UPS5000-E-(30 kVA–120 kVA)-FM
User Manual
Figure 3-8 UPS mounting hole positions (unit: mm)
Step 2 Use a hammer drill to drill four holes for installing expansion bolts and then
install four expansion bolts in the holes.
expansion bolt, and
Figure 3-9 Expansion bolt composition
(1) M12 bolt
Knock the expansion bolt into the hole until the expansion sleeve completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Issue 03 (2022-01-30)
Figure 3-10
(2) Spring washer
NO TICE
Copyright © Huawei Technologies Co., Ltd.
Figure 3-9
shows the composition of an
shows how to install an expansion bolt.
(3) Flat washer
3 Installation
(4) Expansion sleeve
56