8. DECOMISSIONING AND DEMOLITION

Before proceeding with the decommissioning disconnect the electrical
supply to the equipment and any other connections there may be and
then move the modules using suitable means such as: forklift trucks,
hoists, and so on.
The machines are made from the following materials: stainless steel,
aluminized steel, glass, ceramic material, rock wool and electrical parts.
For the purposes of demolition therefore the materials have to be
separated in compliance with the norms in force in the place where the
machine is being dismantled.
Separate collection. This product must not be disposed of
with normal household waste. Local RAEE regulations may
provide for separate collection of this kind of product.