Prior to Installing the SPX-CABFIN
6
Backfill and tamp the trench to hold the conduits or cables firmly in place.
7
Construct and place the leveling stakes (refer to the template label for locations).
8
Remove the template(s), and level the pad form.
The pad top surface should be approximately 6 inches (152 mm) above the gravel base, and 2 inches (51 mm)
above the final grade.
9
Place wire mesh (6 x 6, 4 gauge) in the form; ensure that the mesh is vertically centered in the form as shown
in
Figure 6 on page
No. 3 (3/8-inch) or larger reinforcing rod, with high chairs placed on 15-inch (380 mm) centers,
may be used in place of wire mesh.
10
Place the template(s) in the form, and fasten the template(s) to wooden stakes.
11
Position the conduit and cable as required in the cable entry box(es) or appropriate template openings.
Ensure that the conduit ends extending through the template are perpendicular to the template
surface and centered in the cables boxes.
12
Level the template(s) on the stakes so that the tops of the templates are flush with, to 1/4 inch (6 mm) above
the top of the form.
13
Ensure that the conduits extend approximately 2 inches (51 mm) above the template(s).
Cover the conduit openings to keep concrete from entering during the pour.
8
Figure 5. Power Cabinet Template
9.