Place the conduits, cables, ground rod(s), and ground wire(s) as indicated in the engineering work prints.
Position the conduits horizontally to accommodate four 4-inch conduits. If fewer than four conduits are used,
install those closest to the center of the template first.
2
Place a ring ground system around the proposed foundation pad location according to local practices and
building safety codes.
3
Lay the SPX-CABFIN cabinet template on the ground over the conduits, and slip the conduits (or cables) into
the hole(s) for the cable entry box(es) to locate their positions.
4
Construct the concrete form as shown in
Refer to the template label for dimensions.
5
Lay the power transfer cabinet template (if used) over the conduits, in one corner of the pad, to locate the
corner as shown in
Refer to the template label.
SPX-CABFIN01, SPX-CABFIN04
F
ORM
Figure 4
Figure 5 on page
8.
146"
(3708 mm)
132"
(3353 mm)
Figure 4. Foundation Pad Preparation
November 9, 2001
Prior to Installing the SPX-CABFIN
18"
(457 mm)
Template
52"
(1321 mm)
7