1U1N Configuration Equipment Installation
Hardware Installation Guide
36
3. Rotate the system downward until all the rail standoffs are seated in the J-slots.
Figure 13 Install the system in the rails
4. Push the system inward until the lock levers click into place.
5. Pull the blue slide release lock tabs forward on both rails and slide the system
into the cabinet. The slam latches will engage to secure the system in the
cabinet.
Figure 14 Slide the system into the cabinet
Need help?
Do you have a question about the EMC ScaleIO Ready Node 14G and is the answer not in the manual?