Section 1: Assembly & Set-Up
39294
Counterbalance Valve (Optional)
Refer to Figure 1-5:
IMPORTANT: Make sure ports LB & LR on counter
balance valve (#12) are on the left-hand side with LB
port at the bottom and LR port at the top and that
counter balance cartridge (#14) is on the right-hand
side at the top as shown.
11. Attach valve mounting bracket (#1) to screen
guard (#16) with four 5/16"-18 x 1" GR5 hex head
bolts (#5) and hex nylock nuts (#4). Tighten nylock
nuts to the correct torque.
12. Screw adapters (#11) to ports (LB, LR, RB, & RR) on
counterbalance valve (#12) until tight.
13. See Important note above. Attach counterbalance
valve (#12) to valve mounting bracket (#1) with two
5/16"-18 x 2 1/2" GR5 hex head bolts (#6) and hex
nylock nuts (#4). Tighten nylock nuts to the correct
torque.
14. At port (LB), tighten hose (#7) to adapter (#11).
15. At port (LR), tighten hose (#9) to adapter (#11).
16. At port (RB), tighten hose (#8) to adapter (#11).
17. At port (RR), tighten hose (#10) to adapter (#11).
18. Attach hydraulic hose clamps (#2) to spill screen (#1)
as shown with 5/16"-18 x 1 3/4" GR5 hex head
bolts (#3) and hex nylock nuts (#4). Do not tighten
nylock nuts at this time.
12
Series: GB25, GBE25, and GBE30 Grapple Buckets 380-192M
Table of Contents
Counterbalance Valve (Optional)
Figure 1-5
19. Make required adjustment to hydraulic
hoses (#7, #8, #9, & #10) and draw clamps (#2) up
tight by tightening hex nylock nuts (#4). Do not crush
hoses.
Refer to Figure 1-4 on page 11:
20. Tighten elbow fittings (#5A & #5B) to hydraulic
cylinders (#11).