Autotest
Description
(CEI 0-21)
The 'Autotest' can be used to check the protective function required by the Italian stand-
ard for monitoring the voltage and frequency limits as well as the trip limits of the inverter
during commissioning. During normal operation, the inverter constantly checks the cur-
rent voltage and frequency actual value of the grid.
After the start of the autotest, various individual tests run automatically one after the oth-
er. Depending on grid conditions, the duration of the test is approx. 15 minutes.
IMPORTANT!
The inverter may only be commissioned in Italy after a successful autotest (CEI 0-21). If
the autotest is not passed, no feed-in operation may take place. If the autotest is started
once, it must be completed successfully. The autotest cannot be started during emer-
gency power mode.
VAC inner
limit max
VAC inner
limit min
FAC inner
limit max
102
V+/GND
IO
0
2
4
v
v
+
+
1
3
5
GND
GND
DNO Feedback
not used
DNO Rules
Rule 1
0
2
4
6
1
3
5
7
Active Power
100
Power Factor (cos φ)
1
DNO Feedback
Rule 2
0
2
4
6
1
3
5
7
Active Power
0
Power Factor (cos φ)
1
DNO Feedback
IMPORT
EXPORT
Test to check the maximum voltage in the phases
Test to check the minimum voltage in the phases
Test to check the maximum frequency
I
6
8
10
7
9
11
8
10
9
11
cap
8
10
9
11
cap
None
0
1
None
None
2
None
3
4
None
None
5
None
6
7
None
IO control
8
None
9
10
None
None
11

Advertisement

Table of Contents
loading

Table of Contents