Settings on the Fronius Symo GEN24 inverter website:
1
2
Example 2a: Fronius SnapINverter > Fronius Symo GEN24
Two primary meters are required for the inverters.
The power values shown are an example. Inverter configurations with power values oth-
er than those shown in the example are possible, taking into account the criteria for this
example.
IMPORTANT!
With two primary meters at the feed-in point without a secondary meter, Fronius SnapIN-
verter and Fronius Symo GEN24 inverters cannot be displayed as a combined PV sys-
tem in Solar.web. Two individual PV systems must be created in Solar.web.
92
Configure the primary meter at the feed-in point in the "Device configuration" →
"Components" menu.
Activate the limit for the entire system in the "Safety and grid regulations" → "Export
limitation" menu. Enter the DC nominal output of the entire PV system in the "Total
DC system power" input field. Enter the percentage value (50%, 60% or 70%) in the
"Maximum permitted feed-in power of the entire system" input field.