Manually push the BAT cables through the
DC bushings.
* Connect the ground conductor of the bat-
tery to an external point (e.g. switch cabin-
et). In doing so, the minimum cross sec-
tion of the battery's ground conductor must
be observed.
IMPORTANT!
Before stripping the insulation, push the
cables through the DC bushings to prevent
individual wires being bent or broken.