Draining The Boiler On The Dhw Side - Viessmann Vitodens 222-F Installation And Service Instructions For Contractors

Gas condensing storage combi boiler natural gas and lpg version
Table of Contents

Advertisement

Checking the anode earth current with an anode...
3. Connect the tester (up to 5 mA) in series across
tab
B
and earth cable
If the current measures
magnesium anode is OK.
If the current measures < 0.3 mA or if there is no
current at all, inspect the protective magnesium
anode visually (see page 46).

Draining the boiler on the DHW side

Fig. 37
A
.
0.3 mA the protective
>
Commissioning, inspection, maintenance
(cont.)
1. Connect the hose to the drain valve and route it
into a suitable container or drain outlet.
Note
Ensure adequate ventilation in the DHW pipework.
2. Turn drain valve from lever position
tional) to lever position
Lever position
: the DHW circuit in the appli-
B
ance excluding the DHW cylinder is drained via
the cold water connection.
Lever position
: the DHW circuit in the appli-
C
ance and DHW cylinder are drained via the hot
water connection. The cold water connection
remains filled.
(opera-
A
or
as required.
B
C
45