Turn the pump output downwards for external bath circulation.
-
Fit the hose section of the pump connection set onto the outflow elbow
-
and place the pump connections in the position of the removed blind
flange.
Push the holed flange under the pump connections and fasten it with
-
two cross-head screws to the underside of the control head.
Use the flat seal. Make sure the seal is in the correct position. On one
-
side of the seal there are two steps:
They must be positioned on the side of the display.
Refit the control head onto the bath bridge with the two cross-head
-
screws.
Select the division of the pump flow to suit the thermostating task using
-
the selector switch on the front of the control head.
EXT
The position
gives the greatest flow in the external circuit.
INT
With the position
the external flow is throttled to a minimum and the outlet
for the internal bath circulation is fully opened.
INT
With positions between
and external circulation.
ECO Gold
Holed flange
EXT
and
the flow is divided up between internal