Inbetriebnahme
7.

Commissioning

7.1

Final inspection

EN 36/48
POLARIS REMOTE
- for Zone 1/21
POLARIS Remote KVM Analog 15" / 19.1"
For electrical systems the relevant installation and operating specifications (e.g. Directives
2014/34/EU, BetrSichV and the applicable national ordinances, IEC 60 079-14 and the
DIN VDE 0100 series) must be observed.
The operator of an electrical system in a hazardous environment must keep the operating
equipment in an orderly condition, operate it correctly, monitor it and do the required
maintenance and repairs.
Before commissioning the devices, check that all components and documents are there.
Check the following requirements before commissioning the device:
Only open the ex e terminal compartment with terminals for the supply and data line(s)
once it has been ensured that no potentially explosive atmosphere is present and that the
power supply has been turned off.
POLARIS Remote
Has the reinforcement frame between the bracket and enclosure been inserted?
Is there no damage to seals, cable connections or glass panel?
Are the supply and data line(s) correctly wired?
Is the PE connection correctly earthed?
Have the supply and data line(s) been tightened in the screw terminals?
Are all terminal compartments closed?
Have all cable glands been tightened and all open cable entries closed with blanking
plugs?
Local unit
Is the network box connected to the local unit via patch cable?
Are the data lines for USB, DVI and the power pack connected?
Only start the POLARIS (if a potentially explosive atmosphere is present) once the final
inspection has been carried out.