System Commissioning

DelREMO-V2.0 commissioning consists of starting up procedure and calibration of the system.
4.1

Steps involved in system commissioning

Following steps are involved in the commissioning procedure of the DelREMO-V2.0. Follow the stepwise
procedure to avoid any mistakes in the commissioning procedure.

4.1.1 System start up precautions

DelREMO-V2.0 works with 24V DC voltage, extra care should be taken while operating the system. Read
and follow precautions mentioned below carefully while starting up the commissioning of the system.
Ignorance of the precautions can cause serious loss to life or equipment.
Serial
no.
1
2
3
4
5
6
ENSURE ALL TOOLS ARE PROPERLY INSULATED BEFORE USING THEM.
NOTE

4.1.2 Starting up procedure

Check all the wire connections for any damage or loose connections, before starting up procedure of
DelREMO-V2.0. Follow the below step wise procedure strictly for startup procedure of DelREMO-V2.0.
Step wise starting process will prevent probability of any mistake or missing any step.
Serial
no.
Steps for Startup precautions
Check all wires again for any possible
loose or wrong connections prior to
commissioning.
Check AC supply to adapter unit is
switched to the "Off" position
Check the frame ground is properly
connected to a permanent earth ground
connection
Check all inverter modules are connecting
in daisy chained array.
Check SIM Card is inserted at SIM 1 slot
(If GSM/GPRS data mode to be used)
Check Antenna is connected to SMA
connector provided on body. (If
GSM/GPRS data mode to be used)
Starting up procedure
Check
Check
16