1)
Only cold water must be supplied to the appliances.
2)
If the mains water pressure exceeds 6 bar, a pressure reducer must be
installed to regulate the outlet pressure to a maximum of 6 bar.
3)
Connect the drain hose to the tray, avoiding sharp bends and keeping a
sufficient slope for regular flow of the drain water.
4)
Connect the 3/8" hose to the mains outlet and then to the water softener
and to the appliance.
N.B. A water softener is indispensable for correct appliance operation, best
coffee in the cup and long life of the components, since it removes scale and
residues from the water that would otherwise shorten their life.
The company is relieved of all and any liability in the event of failure to comply
with the above instructions.
Open the tap and let water flow through the deconcentrator to clear dirt off the
circuit before plug- ging the hose into the pump.
Before using the appliance, check that:
-
the plug is inserted properly into the mains power outlet;
-
the filling hose is correctly connected to the mains outlet and that the water
supply is open. Also check for leaks;
-
the drain hose is positioned according to the above instructions and fixed
by a hose clamp. With the steam tap (B) open, put the on/off switch (D) to
position 1 and wait for the water in the boiler to reach the maximum level set by
the electronic control, which can be visually checked on the level indicator (L). If
the boiler does not fill within the set time-out (90 sec.), the pump stops and the
indicator lights on the control panel start to blink. If this happens, put the on/off
switch (D) to position 0 and then to position 1 per to complete filling of the boiler.
Than put the on/off switch (D) to position 2, which switches on the electric heating
elements to start heating the water.
Wait for steam to come out the steam nozzle (B), then close the tap and, using
the Boiler pressure
gauge, check that the pressure has reached and maintains a value of 0.8:1 bar.
If not, use a screwdriver to turn the pressure switch adjustment screw towards +
or - as shown below.