Site Preparation Guide
Preparing for Installation
Inspect Crate for Damage
Before opening the shipping crate, inspect the crate for signs of exterior damage. Report
evidence of excessive damage to Stratasys and the shipping company.
Required Tools and Equipment
•
Basic hand tools (impact drill or hammer drill with Phillips bit)
•
Utility knife
•
Forklift truck of sufficient size to raise the system from the shipping base
•
Ladder
•
Two or more people
Moving the Crated Printer
The F770 shipping crate is designed to be lifted and moved by forklift from the designated
locations on the shipping base
inches (178 cm) of clearance on all sides.
Warning:
The crated printer weighs 2000 lbs. (907 kg). Make sure that equipment and
personnel are capable of moving the system.