C O M M I S S I O N I N G

7 Commissioning

7.1 Preparatory work

To prepare for commissioning, the following work
must be carried out prior to the connection of
the high voltage power supply:
Check the general condition of the switchgear
for any damage or defects
Visually inspect the switching devices,
withdrawable parts, isolating contacts,
insulating parts, etc
Check the connection between the main
earthing bar and the installation earthing
conductor
Check the paintwork for damage and, where
necessary, touch up as described in section 8.5
Remove all residues of materials, foreign bodies
and tools from the switchgear
Clean the switchgear, rubbing down the
insulating parts with a soft, dry, clean, non-fraying
cloth. Remove any greasy or sticky dirt as
described in section 8.4
Correctly remount all covers etc. removed during
the assembly and testing procedures
Remove the transport caps on the vacuum
circuit-breakers if they are still fitted
Perform AC voltage testing of the main circuits
according to IEC 600271-200 where necessary.
Pay special attention to the voltage transformers
and cables, etc. during this procedure
Switch the auxiliary and control voltage on
Carry out testing operations on switching
devices manually or by electrical control, and
simultaneously observe the relative position
indicators
Check the mechanical and electrical interlocks
for effectiveness without using force
Set the protective devices in the switchgear
to the required values and check their function
with test equipment
For any other matters regarding operation of
the withdrawable circuit-breaker part and testing
facilities for the withdrawable part, please see
section 8.5
Instruct local operators regarding the basic
details in the regular handling of the switchgear
Check readiness for operation and the switching
status of electrical systems upstream and
downstream of the switchgear
Depending on the allocation of responsibilities,
it may also be necessary to check the following
equipment in areas adjacent to the switchgear:
-
Power cables
-
Auxiliary cables
-
Auxiliary power source
-
Remote control system
-
Complete earthing system
-
Switchroom equipment
-
Switchroom conditions

7.2 Start-up

Comply with all relevant safety regulations
Ensure that the circuit breakers in the system
are in the OFF position
Remove any existing earthing and short-circuiting
connections in the critical switching area
Energize the feeder cables
Connect the switchgear step by step, observing
the signals and indicators
Check that the relative conductors are in phase
and, where necessary, when there are several
incoming feeder cables and switchgear sections
Carry out all measurements and check the
functions which depend on the connection of
a high-voltage power supply
Watch out for irregularities of any kind
47