Section 5: Troubleshooting

Table 5-23 HV Is Switched On but FPS Front Panel HIGH VOLTAGE ON LED Fails To Light

Symptoms
HVPS Front Panel: HV switched on, with LEDs indicating nominal HVPS state
FPS Front Panel: HIGH VOLTAGE ON LED is unlit
Possible Cause
1. FPS is not powered up.
2. HV IS ON signal is not present at
FPSB connector J102.
3. Fault condition(s) whose investigation
requires removal of HVPS top cover

Table 5-24 FPS Is Switched On but Its POWER ON LED Fails To Light

Symptoms
HVPS front panel: FILAMENT POWER LED on turns red
FPS #1 front panel: POWER ON LED on fails to light when FPS is switched on
EBC displays FPS Gun Ctl Go On Timeout alarm message
For additional information about this fault mode, see Ishikawa Diagram #16.
Possible Cause
1. HVPS rear panel connector J1 not
supplying 208 V ac power
2. HVPS rear panel fuses F1 and/or F2
blown.
3. Faulty FPS power cable.
4. Blown fuses on FPS input power line. 4. Check and replace fuse(s) as necessary, as described in section 5.5.
5. Fault condition(s) whose investigation
requires removal of HVPS top cover
5.5

FPS Fuse Replacement Procedure

To check the input power fuses and replace them as necessary, follow the instructions provided
below.
0101-8242-0, Rev. C
1. Make sure that FPS is switched on. If switch is on, POWER ON LED is lit,
and HV is switched on, proceed to Step 2. If FPS switch is in the ON
position but the POWER ON LED is not lit, see Table 5-24.
2. Check pins J102 Pin 1 for the HV IS ON signal. If not present, proceed to
Step 3.
3. Contact Temescal Field Service.
1.
Disconnect FPS power cable from HVPS J1 and check J1 for 208 V ac output. If no
voltage or incorrect voltage is indicated, proceed to Step 2. If voltage is correct,
skip to Step 4.
2.
Check fuses and replace as necessary. After replacing either fuse, repeat Step 1 of
this procedure. If correct voltage is then detected at J1, reconnect power cable
between J1 and FPS #1.
3. Reconnect the FPS power cable to J1 and disconnect it from the FPS.
Measure the female end of the cable for 208 V ac. Replace cable as
necessary.
5. Contact Temescal Field Service.
Step
Action
1
Set the FPS ON/OFF switch to the OFF position.
7
Switch off the facility breaker providing AC power to the FPS.
8
Unplug the input power cable from its receptacle on the FPS front
panel.
5-29
5.5 FPS Fuse Replacement Procedure
Procedure