Commissioning - Mira Realm Installation, Operation, Maintenance Manual

Table of Contents

Advertisement

Section
7
1. Maximum temperature setting
This thermostatic shower control has been fully performance tested and the maximum
temperature has been pre-set to approximately 42°C under ideal installation conditions
at the factory. Site conditions and personal preference may dictate that the maximum
temperature has to be reset.
To reset the maximum temperature ensure that an adequate supply of hot water is
available at a temperature at least 10°C in excess of that required from the shower
control. Turn the lever fully anti-clockwise then check the temperature at the discharge
point, (allowing sufficient time for hot water to reach the hot inlet of the shower control).
If the temperature is correct, turn the lever fully clockwise to the off position as no
further adjustment is necessary.
If the maximum temperature achieved at the discharge point is unsatisfactory then
adjust the maximum temperature as follows:-
Grub
Screw
Cover
Grub
Screw
Lever
Hexagon
Spindle
Lever
16

Commissioning

1.1. Before making any adjustments
ensure that upon installation the
correct flow regulators have been
fitted. Refer to the section
Installation.
1.2. Turn the lever fully anti-clockwise
to the hot position.
1.3. Carefully unscrew the grub screw
cover and remove.
1.4. Use the 2.5 mm A/F hexagon wrench
(supplied) to loosen the grubscrew.
1.5. Remove the lever housing from the
hexagon spindle.